Sl. No. |
NAME OF THE PROJECTS |
District |
Division |
Name of Executing Agency |
1 |
Installation of 3rd 315 MVA at Mendhasal S/s. |
Khurda |
Bhubaneswar |
M/s Mavin switchgear & control, Aurangabad. |
2 |
220/132/33 KV S/S at Pratapsasan |
Khurda |
Bhubaneswar |
M/s Lanco infratech Ltd, Gurugaon. |
3 |
132kV line from Nuapatna to Banki |
Cuttack |
Bhubaneswar |
M/S GPIL JV S.B.Electrostructure |
4 |
132/33kV Satasankha S/s |
Puri |
Bhubaneswar |
M/s Flowmore Limited, Ranchi JV WITH M/S COBRA |
5 |
220kV line from Pandiabil to Pratapsasan |
Khurda |
Bhubaneswar |
M/s. Fedders Lloyd Corporation Limited, New Delhi |
6 |
132/33kV GIS S/s at Unit-VIII, Bhubaneswar |
Khurda |
Bhubaneswar |
M/s G E (T&D) India Ltd |
7 |
132/33kV GIS S/s at Rasulgarh/Mancheswar, Bhubaneswar |
Khurda |
Bhubaneswar |
M/s G E (T&D) India Ltd |
8 |
220/33 KV Grid S/S at Narasinghpur |
Cuttack |
Cuttack |
M/s Tesla Tranformer Ltd, Bhopal jv with M/s Jagabandhu Enterprisers Ltd, BBSR |
9 |
220kV LILO of Meramundali-Bhanjanagar DC line for Narsinghpur |
Cuttack |
Cuttack |
M/s Velcro Electrical Manufacturer Pvt. Ltd, Bhubaneswar |
10 |
132/33kV S/s at CDA Cuttack(Brajabiharipur) |
Cuttack |
Cuttack |
M/s A.K.Das & Associates, Bhubaneswar |
11 |
132kV Olavar-Chandbali Line |
Bhadrak |
Cuttack |
M/s Sidhartha Engineering, Bhubaneswar |
12 |
220/132/33 KV S/S at Aska |
Ganjam |
Berhampur |
M/s Flowmore Limited, Ranchi JV WITH M/S COBRA |
13 |
220/33 KV S/S at Baliguda |
Kandhamal |
Berhampur |
M/s Flowmore Limited, Ranchi JV WITH M/S COBRA |
14 |
132/33 KV Grid S/S at Chikiti |
Ganjam |
Berhampur |
M/s Flowmore Limited, Ranchi JV WITH M/S COBRA |
15 |
132/33kV Substation at R.Udayagiri |
Gajapati |
Berhampur |
M/s Siddhartha Engg Ltd Jv with M/s Deepak Cables Ltd, Bangalore |
16 |
220/33kV Daspalla S/s |
Nayagarh |
Berhampur |
M/s Tata Projects Limited |
17 |
132/33kV G.Udayagiri S/s |
Kandhamal |
Berhampur |
M/s A K Das & Associates, Bhubaneswar |
18 |
132kV Paralakhemundi-R Udaigiri Line |
Gajapati |
Berhampur |
M/s JD Infratech, Balasore |
19 |
132kV Aska-Digapahandi Line |
Ganjam |
Berhampur |
M/s Bharati Construction, Bhubaneswar |
20 |
220/132/33 KV S/S at Goda |
Dhenkanal |
Angul |
M/s Ashtabinayak, Mumbai |
21 |
132kV line from Phulbani to Boud |
Kandhamal |
Angul |
M/s Sidhartha Engineering, Bhubaneswar |
22 |
400/220kV Meramundali B GIS S/s |
Angul |
Angul |
M/s Siemens Limited |
23 |
20/132/33kV Kiakata S/s |
Angul |
Angul |
M/s Tata Projects Limited |
24 |
132 KV line from Bhadrak to Anandapur |
Bhadrak |
Keonjhar |
M/S GPIL, Bhubaneswar |
25 |
220/33kV Keonjhar SIS S/s |
Keonjhar |
Keonjhar |
M/s Toshiba Transmission and Distribution Systems(India) Ltd, Medak |
26 |
220kV DC line from Keonjhar PG to Keonjhar S/s |
Keonjhar |
Keonjhar |
M/s JD Infratech, Balasore |
27 |
Installation of 3rd ICT at Duburi |
Jajpur |
Keonjhar |
M/s A.K.Das & Associates, Bhubaneswar |
28 |
132/33 kV Grid S/S at Agarpara |
Bhadrak |
Balasore |
M/s Jagabandhu Enterprisers Pvt Ltd, Bhubaneswar |
29 |
132/33Kv S/S at Udala |
Mayurbhanj |
Balasore |
M/s Mahashakti Energy Ltd. JV with Powercon Projects Associates. |
30 |
132kV Line from Kuchei to Bangiriposi |
Mayurbhanj |
Balasore |
JD Construction, Balasore |
31 |
132/33 KV S/S at Betanoti |
Mayurbhanj |
Balasore |
M/s. Fedders Lloyd Corporation Limited, New Delhi JV with M/s. Jagbandhu Enterprisers Private Limited |
32 |
132/33kv Chandbali GIS S/s |
Bhadrak |
Balasore |
M/s G E (T&D) India Ltd |
33 |
220/132/33kV Dhamra S/s |
Bhadrak |
Balasore |
|