ODISHA POWER TRANSMISSION CORPORATION LIMITED
(A Govt. of Odisha Undertaking)
CIN No.:U40102OR2004SGC007553
land land land
Latest News
Page last modified on : 17/Mar/2018 12:59

Planning Process

  • Preparation of data.
  • Detail load Forecasting . (The forecast of long term demand for electricity is a fundamental prerequisite for the development of a secure and economic power system. The said forecast is being revised in each year and submitted to OERC as per Grid Code taking due care of new policies of Govt. and changes in the socio-economic trends.)
  • Locating load centers
  • Identifying sub-station location and voltage class.
  • Staging study for base year, intermediate year and horizon year
  • The load flow study is prepared for different condition of generation schedule including Short Circuit study, transient stability analysis.
  • Development of upstream/Down stream network
  • Consideration of addition of system elements to avoid system constraints and to meet the planning criteria.

Overall the planning is based on the guidelines as prescribed by Central Electricity Authority and Regulatory Commission.

          The activities to be carried out has been laid down in  the standard planning procedures (SPPs) approved by GRIDCO in December’2000. Some of these are statutory in nature i.e. needs to be submitted to OERC within a prescribed time frame, The said SPP are being followed by OPTCL.

THE WORK EXECUTED BY LTPC SO-FAR AS FOLLOWS;.

(1)   System Study.
                        System studies for the first time for any existing/new users who are connected/proposed to be connected to the Orissa Grid net work, conducting load flow study, shut circuit study, Transient Study analysis in different conditions. As on to-day, this branch has conducted almost 150 nos system studies for some users on their request on prepaid basis.

(2)   Long Term Demand Forecast.     
Long Term Demand Forecast (LTDF) report for coming 10years is being processed in each year based on the data of coming 5 years received from the DISCOMs. The LTDF report for the period 2010-19 is  submitted to Hon’ble OERC during May’10 for kind approval.
(3)   Long Term Perspective Transmission Plan.       
          OPTCL ensures development of an effective and economical system of Intra-State and Inter-State transmission lines for smooth flow of electricity from generating station to Load center.
          The infrastructure of  OPTCL network is as follows.

  1. 95nos. of Grid Sub-Stations with transformation capacity of 8845MVA.
  2. 10902Ckt. KMs of transmission lines of 400KV,220KV and 132KV rating.

The present peak demand of the state is around 3000MW, which is handled by the existing network of equipment of the system. To improve the low voltage problem in some of the Grid Sub-Stations, action has already been initiated to install 275MVAR shunt capacitors.

According to the long term demand forecast, the peak demand of Orissa at the end of 11th and 12th plan period will be to the tune of 4459MW and 6363MW respectively. Besides the above projection , in the mean time a number of IPPs have signed MOUs with Govt. of Orissa to install power plants in Orissa. It is expected that at the end of 12th plan period the quantum of power generated by these IPPs will be of 20000MW and Orissa will avail the state share of 25% i.e. about 5000MW . Therefore Orissa Transmission System needs to be planned to handle the upcoming load which will cater to the load requirement of different up-coming industries and schemes like REC,RGGVY and BGJY.

Planning is required for a healthy transmission system to extend uninterrupted, quality and reliable power supply. Alternative source of supply is to be made available at all Grid Sub-Stations to avoid total power failure in the region due to fault in single source of supply. All the Grid Sub-Stations is to operate in a ring arrangement. In view of the above , OPTCL has prepared a comprehensive system planning of its network, by M/S PRDC Ltd., Bangalore. Planning is made to prevent overloading wherever possible by load diversion and taken up innovative measures for system loading of its existing network. Effective utilization of new lines and their impact on transmission loss is being taken care.